Allied & ICAR Exam Bank • ALLIED_0426 MCQ • 1 Mark

Section 4: Soil and Water Conservation Engineering

Hydrology and Runoff

Subtopic: Hydrograph Analysis and Watershed Routing

Question Statement:

A Unit Hydrograph (UH) of duration $D$ is the direct runoff hydrograph produced by:

Options:

  • (A) Unit depth ($1\text{ cm}$ or $1\text{ mm}$) of direct runoff resulting from an excess rainfall occurring uniformly over the catchment at a constant rate for duration $D$
  • (B) $1\text{ m}^3/\text{s}$ peak discharge
  • (C) $1\text{ cm}$ of gross rainfall regardless of infiltration
  • (D) Rainfall of 1 hour duration

Answer Key:

A

Step-by-Step Solution & Explanation

Unit hydrograph represents direct runoff resulting from exactly $1\text{ cm}$ (or $1\text{ mm}$ in modern SI units) of effective/excess rainfall generated uniformly over the catchment in duration $D$.