Allied & ICAR Exam Bank • ALLIED_0435 NAT • 2 Marks

Section 4: Soil and Water Conservation Engineering

Hydrology and Runoff

Subtopic: Hydrograph Analysis and Watershed Routing

Question Statement:

The routing coefficients in the Muskingum equation $O_2 = C_0 I_2 + C_1 I_1 + C_2 O_1$ must satisfy the condition $C_0 + C_1 + C_2 = 1.0$. If $C_0 = 0.05$ and $C_1 = 0.45$, the value of $C_2$ is:

Answer Key:

0.5

Step-by-Step Solution & Explanation

$C_2 = 1.0 - (0.05 + 0.45) = 1.0 - 0.50 = 0.50$.