In a Parshall flume, flow discharge can be measured using only a single upstream head measurement ($H_a$) provided the submergence ratio ($H_b / H_a$) does not exceed:

Options:

  • (A) $0.60$ for small flumes ($1-3\text{ in}$) and $0.70$ for flumes of throat width $1-8\text{ ft}$
  • (B) $0.95$
  • (C) $0.10$
  • (D) $0.30$

Answer Key:

A

Step-by-Step Solution & Explanation

Free-flow conditions exist up to $60-70\%$ submergence; beyond this critical transition, modular flow ceases and downstream head $H_b$ must also be recorded.