Allied & ICAR Exam Bank • ALLIED_0718 MCQ • 1 Mark

Section 7: Dairy and Food Engineering

Thermal Processing and Kinetics

Subtopic: Thermal Processing and Kinetics

Question Statement:

The Flow Diversion Valve (FDV) installed at the exit of the holding tube in an HTST pasteurizer automatically diverts milk back to the raw milk balance tank whenever:

Options:

  • (A) Milk temperature at the holding tube exit drops below the statutory legal setpoint (e.g.,
    lt; 72^\circ\text{C}$)
  • (B) Milk fat is too high
  • (C) Flow velocity is zero
  • (D) Milk pressure exceeds 10 bar

Answer Key:

A

Step-by-Step Solution & Explanation

If the temperature sensor detects milk below $72^\circ\text{C}$, the pneumatic FDV diverts flow to the balance tank to ensure sub-pasteurized milk never enters the cooling/packaging section.