Question Statement:

In a structural drop spillway, cut-off walls and toe walls are provided primarily to:

Options:

  • (A) Prevent piping and seepage flow beneath the structure and resist sliding
  • (B) Increase the flow discharge over the weir crest
  • (C) Provide an anchor for trash racks
  • (D) Serve as decorative abutment facings

Answer Key:

A

Step-by-Step Solution & Explanation

Cut-off walls extend deep into firm subgrade to lengthen the percolation path (seepage creep length) to eliminate piping failure and anchor the floor against sliding under hydrostatic thrust.