The floor of the straight drop spillway stilling basin is placed below the downstream channel bed level to:

Options:

  • (A) Ensure sufficient tailwater depth to submerge and contain the hydraulic jump within the basin
  • (B) Allow fish to spawn inside the basin
  • (C) Prevent all sediment from passing downstream
  • (D) Reduce the total concrete thickness

Answer Key:

A

Step-by-Step Solution & Explanation

Depressing the apron ensures that the downstream tailwater depth meets or exceeds the required sequent depth $y_2$, preventing the hydraulic jump from being swept out into the unprotected downstream gully channel.