Question Statement:

In a project budget waterfall analysis, base estimate was Rs 80 lakh, scope additions contributed +Rs 15 lakh, design optimization saved -Rs 8 lakh, and contingency added +Rs 5 lakh. The final project cost was:

Options:

  • (A) Rs 92 lakh
  • (B) Rs 90 lakh
  • (C) Rs 95 lakh
  • (D) Rs 88 lakh

Answer Key:

A

Step-by-Step Solution & Explanation

Final cost $= 80 + 15 - 8 + 5 = 92$ lakh rupees.