Allied & ICAR Exam Bank • ALLIED_3323 NAT • 2 Marks

Section 4: Soil and Water Conservation Engineering

Soil and Water Erosion

Subtopic: Earthen dams

Question Statement:

In Universal Soil Loss Equation A = R*K*LS*C*P, a plot #16 has R = 250, K = 0.3, LS = 2.0, C = 0.10, and P = 0.5. The estimated annual soil loss A in tonnes/ha/year is:

Answer Key:

7.50

Step-by-Step Solution & Explanation

A = 250 * 0.3 * 2.0 * C * 0.5 = 75 * C = 7.50 t/ha/yr.
← Previous (ALLIED_3322) Next (ALLIED_3324) →

Practice In Authentic CBT Exam Interface

Test your skills under authentic timed conditions with live scoring and AIR percentile ranking.

Launch CBT Mock Test