Question Bank • QB_DFE_031 MSQ • 2 Marks

Section 7: Dairy and Food Engineering

Unit Operations in Dairy and Food Engineering

Subtopic: Pasteurization

Question Statement:

Which of the following engineering and sanitary provisions are mandatory in continuous High-Temperature Short-Time (HTST) milk pasteurization systems?

Options:

  • (A) A flow diversion valve (FDV) located downstream of the holding tube that automatically diverts sub-legal temperature milk back to the balance tank.
  • (B) Maintaining pasteurized milk pressure in the regenerator at least $7\text{ kPa}$ ($1\text{ psi}$) higher than raw milk pressure to prevent cross-contamination in case of plate leaks.
  • (C) A holding tube sloped upward toward the flow diversion valve (at least $2\text{ cm/m}$) to eliminate air pockets.
  • (D) Direct contact between raw boiler steam and milk inside the holding tube.

Answer Key:

A, B, C

Step-by-Step Solution & Explanation

• A, B, and C are mandatory regulatory standards for HTST pasteurization plants. • D is prohibited: Raw industrial boiler steam contains chemical additives (scale inhibitors, amines) that cannot contact food directly. Steam must be culinary-grade and is only used in jacketed plates or specialized direct infusion chambers, never raw boiler steam in holding tubes.
← Previous (QB_DFE_007) Next (QB_DFE_030) →