Question Statement:

A canal diversion structure supplies $100\text{ m}^3$ of water at the reservoir head. The volume of water delivered to the agricultural field plot is $80\text{ m}^3$, out of which $60\text{ m}^3$ is beneficially stored in the crop root zone. The overall project irrigation efficiency is ________ $\%$ (round off to one decimal place).

Answer Key:

60.0

Step-by-Step Solution & Explanation

Conveyance efficiency $\eta_c = \frac{W_f}{W_r} \times 100 = \frac{80}{100} \times 100 = 80.0\%$. Field application efficiency $\eta_a = \frac{W_s}{W_f} \times 100 = \frac{60}{80} \times 100 = 75.0\%$. Overall project efficiency is: $\eta_{proj} = \eta_c \times \eta_a = \frac{W_s}{W_r} \times 100 = \frac{60}{100} \times 100 = 60.0\%$
← Previous (QB_SUB_IDE_0184) Next (QB_SUB_IDE_0187) →

Practice In Authentic CBT Exam Interface

Test your skills under authentic timed conditions with live scoring and AIR percentile ranking.

Launch CBT Mock Test