Question Bank • QB_EXP_SWCE_GUL_002 MCQ • 1 Mark

Section 4: Soil and Water Conservation Engineering

Gully Control Structures & Drop Spillways

Subtopic: Temporary vs permanent gully control structures

Question Statement:

Which of the following is classified as a permanent soil conservation structure for gully stabilization?

Options:

  • (A) Drop inlet / pipe spillway
  • (B) Woven wire check dam
  • (C) Loose rock check dam
  • (D) Brushwood check dam

Answer Key:

A

Step-by-Step Solution & Explanation

Drop inlet (pipe spillway), drop spillway, and chute spillways constructed with reinforced masonry or concrete are permanent structures designed for 25-50 year recurrence floods. Woven wire, loose rock, and brushwood dams are temporary/semi-permanent stabilizing structures.