A contractor undertakes to excavate a drainage channel of length $12\text{ km}$ in $80\text{ days}$ by employing 60 laborers. After 50 days, only $6\text{ km}$ of the channel is completed. The number of additional laborers required to complete the remaining excavation on schedule is ________ (answer in integer).