Question Bank • QB_IDE_GATE_001 MCQ • 2 Marks

Section 5: Irrigation and Drainage Engineering

Irrigation Water Conveyance and Application Methods

Subtopic: Design of irrigation channels and underground pipelines

Question Statement:

Match the Water Measurement Structures in Group-I with their Governing Proportionality in Group-II: $\begin{array}{|ll|ll|}\hline \textbf{Group-I (Structure)} & & \textbf{Group-II (Discharge Proportionality)} & \\ \hline \text{P. Rectangular Sharp-Crested Weir} & & \text{1. } Q \propto H^{5/2} \\ \text{Q. } 90^\circ \text{ V-Notch Weir} & & \text{2. } Q \propto H^{3/2} \\ \text{R. Submerged Orifice} & & \text{3. } Q \propto H^{1/2} \\ \hline \end{array}$ Select the CORRECT matching pair:

Options:

  • (A) P-2, Q-1, R-3
  • (B) P-1, Q-2, R-3
  • (C) P-2, Q-3, R-1
  • (D) P-3, Q-1, R-2

Answer Key:

A

Step-by-Step Solution & Explanation

Open Channel Measurement Head-Discharge Exponents: - **Rectangular Weir**: $Q \propto H^{3/2}$ (2). - **V-Notch Weir ($90^\circ$)**: $Q \propto H^{5/2}$ (1). - **Submerged Orifice**: $Q \propto \sqrt{H}$ (3). Correct match: **P-2, Q-1, R-3**.
← Previous (QB_IDE_EXP_012) Next (QB_IDE_EXP_073) →

Practice In Authentic CBT Exam Interface

Test your skills under authentic timed conditions with live scoring and AIR percentile ranking.

Launch CBT Mock Test