Section 4: Soil and Water Conservation Engineering
Soil and Water Erosion
Subtopic: Terraces and bunds
Question Statement:
Contour bunds are to be constructed on agricultural land with a uniform land slope $S = 4\%$. Using the standard empirical formula for vertical interval $VI = \left( \frac{S}{3} + 2 \right) \times 0.3\text{ m}$, the horizontal spacing between successive bunds is ________ $\text{m}$ (answer in integer).